HB1042: Relating to the cessation of tolls by toll project entities in certain circumstances.
Filed 2026-11-10 · Author: Shaheen
- Toll projects must stop charging tolls once construction and acquisition costs are paid and the project's bonds are paid or fully set aside.
- Bonds count as covered if paid off, or if enough money is held in a trust fund for bondholders.
- A toll project entity may not change a financing or other agreement to push back the date tolls must end.
- After tolls end, the project joins the state highway system and the Texas Department of Transportation maintains it, if the Legislative Budget Board finds the state has the resources.
- Instead, a county where the project sits may take it into its road system, if the Legislative Budget Board approves the county's request.
- If neither happens, the entity operating the project must keep maintaining it without tolls.
- A toll project entity may keep charging tolls if costs and bonds are paid only for some segments, and it signs a deal for more segments at least 30 days before the end date.
- Tolls must then stop once all added segments are finished and all costs and bonds for every segment are paid.
- The bill removes Sections 284.008(c) and (d) of the Transportation Code.
- By September 1, 2028, the Texas Department of Transportation must study and report on the costs of ending tolls, working with the Legislative Budget Board.
- The report must list all Texas toll roads and the projected date each must be toll-free.
- The report must also give projected maintenance and operation costs of adding each road to the state highway system.
Summary written with AI from the bill’s official text as filed. The official text is the one that counts.