- The bill covers large data centers: ones using 75 megawatts of power or at least 300,000 gallons of water in 30 days.
- Operators must register each covered data center with the Texas Commission on Environmental Quality (TCEQ) at least 120 days before it opens.
- Operators must file a water resource impact assessment with registration, covering water sources, expected use, wastewater, and effects on local supply.
- Operators must also file a facility water conservation plan with measurable goals, leak detection, and a review of water reuse options.
- Operators must report water use to TCEQ each year by March 31, with monthly figures by source.
- Operators must send copies of filings to affected counties, cities, groundwater districts, and water providers within 10 business days.
- TCEQ must run a public website listing covered data centers and their nonconfidential water filings.
- TCEQ must hold a public hearing in the county before a new data center opens or expands, with 30 days' notice and at least 30 days of comments.
- The operator pays the reasonable direct costs of hearing notices and project documents, and TCEQ may charge a fee for its documented direct costs.
- TCEQ must publish a yearly statewide report on data center water use by November 1, starting in 2030.
- TCEQ may issue violation notices and orders and may assess penalties under existing law, but it may not order cuts in otherwise lawful water use.
- The assessment is not a permit and does not approve or deny any water use.