HB949: Relating to requirements and preferences for purchasing construction materials produced in the United States and this state.
Filed 2026-11-09 · Author: Dean
- State agencies and local governments must require U.S.-produced construction materials in public infrastructure projects estimated at $1 million or more.
- For projects of $1 million or less, a state agency or local government may require U.S.-produced materials.
- The requirement goes in the bid documents and the contract. It covers materials permanently built into the project.
- Covered materials include iron, steel, manufactured products, concrete, cement, aggregates, glass, lumber, drywall, copper, aluminum, asphalt, plastics and fiber-optic cable.
- Projects include roads, bridges, water and flood facilities, public buildings, transit, ports, airports, and broadband or utility systems.
- Iron and steel count as U.S.-produced only if every step, from first melting through coatings, happens in the United States.
- A manufactured product counts if made in the U.S. and over 55 percent of its component cost is U.S.-sourced.
- A state agency that requires U.S. materials must also require the contractor to buy Texas products and materials under Section 2155.444. A local government may do so.
- An entity can skip the U.S. requirement by writing that materials are unavailable or not satisfactory, or that it would delay the project or raise costs unreasonably.
- These written exemption decisions are not open to public disclosure. The entity keeps its reasoning and gives it to the comptroller.
- Contracts made in response to a declared state disaster, or involving federal funds, are not covered.
- The comptroller must make rules, collect yearly data on material sources and exemptions, and report to the legislature by December 1 each year.
Summary written with AI from the bill’s official text as filed. The official text is the one that counts.