Texas bills Bills, in plain English.

Every bill of the Texas Legislature with its real stage in the process. The official text is always one click away on capitol.texas.gov.

Who testified on SB191

People and organizations who signed up at a committee hearing to speak or register for, against or on this bill, as listed by the Legislature. Names of private individuals are not shown, only their number.

No committee hearing yet. Witness lists will appear here after the first hearing on this bill. The session opens January 12, 2027.

A bill's path: Filed→ Committee and floor votes→ Law What are these stages? → Glossary

All bills

SB191: Relating to the interconnection of a facility in the ERCOT power region to certain other facilities.

Filed 2026-11-09 · Author: Hall

  • The bill covers connecting a facility in the ERCOT power region (the Texas grid) to a facility outside Texas, or one tied to it.
  • It applies to electric cooperatives, electric utilities, municipally owned utilities, and any other person.
  • Today, the rule covers connections that let more power be imported into or exported out of the ERCOT grid.
  • Under the bill, a connection to a facility outside Texas, or tied to one, needs approval steps first.
  • The connection must not subject the ERCOT power region to additional federal control or jurisdiction.
  • The Public Utility Commission must first find the connection is in the public interest.
  • The commission must consider technical details, public costs to install, operate and maintain it, and its own criteria.
  • The commission must also consider a reliability assessment by the ERCOT independent organization, and any other information it finds appropriate.
  • The applicant must ask for the public interest finding at least 180 days before seeking any federal commission order on the connection.
  • After getting any federal order, the applicant must also get a commission certificate saying public convenience or necessity requires the connection.
  • Today, the person needs only the certificate, applied for at least 180 days before seeking a federal order.
  • As today, the rule does not apply to a facility in service on December 31, 2014.
  • As today, the commission must approve within 185 days an application tied to a federally approved ERCOT–SERC connection settlement.

Summary written with AI from the bill’s official text as filed. The official text is the one that counts.