SB191: Relating to the interconnection of a facility in the ERCOT power region to certain other facilities.
Filed 2026-11-09 · Author: Hall
- The bill covers connecting a facility in the ERCOT power region (the Texas grid) to a facility outside Texas, or one tied to it.
- It applies to electric cooperatives, electric utilities, municipally owned utilities, and any other person.
- Today, the rule covers connections that let more power be imported into or exported out of the ERCOT grid.
- Under the bill, a connection to a facility outside Texas, or tied to one, needs approval steps first.
- The connection must not subject the ERCOT power region to additional federal control or jurisdiction.
- The Public Utility Commission must first find the connection is in the public interest.
- The commission must consider technical details, public costs to install, operate and maintain it, and its own criteria.
- The commission must also consider a reliability assessment by the ERCOT independent organization, and any other information it finds appropriate.
- The applicant must ask for the public interest finding at least 180 days before seeking any federal commission order on the connection.
- After getting any federal order, the applicant must also get a commission certificate saying public convenience or necessity requires the connection.
- Today, the person needs only the certificate, applied for at least 180 days before seeking a federal order.
- As today, the rule does not apply to a facility in service on December 31, 2014.
- As today, the commission must approve within 185 days an application tied to a federally approved ERCOT–SERC connection settlement.