SB383: Relating to the issuance of a preconstruction air quality permit for a major stationary source located in a nonattainment area.
Filed 2026-11-13 · Author: Miles
- The bill adds rules for air quality permits issued before building certain large polluting facilities in areas with poor air quality.
- It applies to building or majorly changing a major stationary source in a federal Clean Air Act nonattainment area.
- A nonattainment area is an area designated under the federal Clean Air Act. The bill applies to facilities located or proposed there.
- When deciding if a facility's emissions will go against the intent of the state's air law, the commission must follow new steps.
- The commission is the Texas Commission on Environmental Quality, which reviews these permits.
- The commission must analyze other locations, sizes, production processes, and environmental control techniques for the facility.
- The analysis must show the facility's benefits significantly outweigh the environmental and social costs of its location, construction, or modification.
- The commission must also consider cumulative impacts if the permit is issued without changes to location, size, processes, or controls.
- "Major stationary source" and "major modification" mean what federal rule 40 C.F.R. Section 51.165 said on January 1, 2027.
- The change applies to permits issued or amended on applications pending at the commission on or after the bill's effective date.
Summary written with AI from the bill’s official text as filed. The official text is the one that counts.