SB461: Relating to the removal of certain power facilities operated on leased property.
Filed 2026-11-20 · Author: Hall
- Today, wind, solar and battery storage companies that lease land must give landowners money set aside to cover removing their facilities.
- The bill would have these companies deliver that money, called financial assurance, to the Texas Commission on Environmental Quality instead of the landowner.
- The assurance would still be payable to the landowner. It would be due when the lease begins, not years later.
- The assurance could only be a bond or another form the landowner finds acceptable. Parent company guaranties and letters of credit are removed as listed forms.
- New Chapter 304 adds the same removal and land restoration duties for energy storage and other renewable power facilities, such as geothermal, on leased land.
- Battery and other energy storage facilities must also cover landowner damage from fire, chemical leaks, thermal runaway or explosion, by assurance or by an insurance policy.
- A licensed independent engineer must estimate removal costs. Updated estimates are due by year 10 and every five years after.
- Companies could not cancel assurance until removal is done, unless they give replacement assurance to the commission.
- A company could ask the commission to release assurance. The commission must inspect the removal and restoration work within 45 days.
- A landowner could ask the commission to order forfeiture of the assurance if the facility is unused and removal work is unfinished.
- After a forfeiture, the commission and the Public Utility Commission of Texas could not issue or renew operating permits for that company's facilities.
- The changes apply to leases made on or after the effective date. Older leases must give assurance to the commission by the lease amendment date or January 1, 2028, whichever is earlier.